How to form & pour Concrete Steps with a Pier Foundation. D.I.Y

C.L.S. All-IN-ONE
129 followers
64 Video Views·Dec 10, 2022
Hey what's up everybody this is CLS All-in-One. I recently replaced my old wooden steps
that were in very poor condition with some concrete steps. This is a five step set of
stairs measuring at approximately three and a half feet tall by five feet wide by eight feet long.
So the first step in this process is building a footing or foundation. Building codes in most
areas will usually require a foundation for concrete entry stairs. In my area I'm required
to have a foundation that's at least 40 inches below the surface because the frost depth can
reach close to three feet in my area. But you will want to keep in mind the building codes will vary
so please check with your local building codes before proceeding with a project such as this.
Foundations for entry stairs are important because they provide support for the heavy
vertical loads and will also keep your stairs from sinking sagging or pulling away from your house.
For my stairs I chose to go with a pier foundation. These are 10 inch concrete building form tubes
and I placed one in each corner of where the staircase footprint will be located. So these
pier footings consist of a hole dug to approximately 40 inches deep with a poured concrete footing at
the bottom with the diameter being at about 16 inches and the depth at 10 inches along with a
half inch rebar cage to reinforce the concrete and a piece of rebar sticking up at about one foot
for the piers to tie into. Then I place the building form tubes on top of the footings
then backfill the sides which is the point I am at right now. The next step will be adding a rebar
cage to the inside of the tubes and after that I'll be filling the tubes with concrete. So right
here we are backfilling the building form tubes and the top of these tubes are just going to be
slightly above ground level. Now it's time to make some half inch rebar cages to go inside these tubes.
They do make some rebar benders but if you don't want to buy one you can just get creative and use
a bench vise or even a truck hitch as I'm using right here to bend the rebar. So what I've done
here is bent three pieces of rebar into the same shape. Then I tied these pieces of rebar together
in a triangular pattern to make a cage. And here's something to keep in mind when making a rebar cage
for a footing or pier. The cage should be at least one and a half inches from all outside edges of the
concrete. Now that the cages are in place it's time to mix up some concrete. For this I'll be using
Quikrete high strength just add water mix and mixing this to a consistency where I can easily
pour this into the tubes. And as I fill the tubes I make sure to pack them tightly to ensure the
concrete fills the entire tube. And at the same time I make sure to keep the cages centered
inside these tubes. Now it's time to add some J-Bowl anchors into the fresh concrete. These
will be used to secure some steel H beams to the top of these piers. After setting all the anchors
in place it's time to wait approximately 24 hours to allow the concrete to dry. So the vertical load
of these concrete stairs will be extremely heavy. Because of this a side support will be necessary
to distribute the main weight of the stairs to each corner pier. So for this I'll be using two
H beams that are three-eighths of an inch thick that will span from the back pier to the front
pier. And for the span going from side to side I will just be using rebar after the forms are in
place. And here's a look at the beams after securing them to the piers. So now I have a foundation that
will support the weight of the concrete stairs. And here is a look at the beginning of the concrete
form process for my stairs. I have used two eight foot sheets of five-eighths OSB. Alternatively you
can just use some regular plywood. But I chose OSB because it gives the concrete a texture that I
prefer over plywood. I have also reinforced the sheets of OSB with numerous 2x4s to stiffen them
and keep the sheets from bowing out. And to secure these forms to the ground to start with
I'm just using some three foot long rebar stakes. But I will be adding some more supports later on.
As you can see here I have the forms perfectly level with each other and placed in the exact
position I want the stairs to be located. To figure out the proper stair rise height and
tread run depth there is numerous stair calculators online that can do the math for you.
A good baseline to start with is a rise of seven inches and a tread run of 11 inches. But depending
on the length and drop of your steps these numbers will more than likely have to be adjusted.
For my stairs to have an even rise and tread run for all five steps I ended up with a seven inch
rise and a ten and a half inch tread run. And I would like to add that you should always check
with your local building codes to make sure what the minimum and maximum is for the run and rise
for stairs located in your area. Another thing I'd like to mention is you should grease any part of
wood forms that will come in contact with the concrete. This will prevent it from sticking when
removing the forms. For this step I'm just spraying the wood with some WD-40 but alternatively you
could use some other products such as diesel fuel applied with a rag. Now it's time to add some cross
support forms for the rise portion of the steps. For this I'm using some two by eights that I have
ripped to seven inches wide along with a 45 degree angle cut on the bottom edge that I'll explain
here in a few. To attach these I've cut some two by four blocks that secure to the OSB and then
secure to the two by eights with the use of three inch screws. And here is a look at the 45 degree
angle cut at the bottom of the rise forms. This allows me to float and finish the concrete step
runs without removing these rise forms. With this 45 degree cut I'm able to reach all the way to the
inside corners of the runs and can leave all the forms in place until the concrete dries and
hardens. But you will want to keep in mind when using this method it will not allow you to finish
the face of each rise. If this is a concern you should just remove the rise forms once the concrete
starts to harden and is ready for finishing. Now it's time to add some anchors to the existing
foundation that will tie in with the concrete steps. For this I'm using some half inch rebar
that has been cut to 16 inches long. I then drill a hole into the foundation at around four inches
deep. Then add construction glue to the inside of the hole then hammer the rebar in place. I then
repeat this process with a piece of rebar located at about every 16 inches across. Now this next step
is somewhat optional but will cut down on the amount of concrete needed. So what I'm doing here
is adding filler to the inside of the step forms. I have outlined the edges with blocks then filled
the center with dirt then added more blocks and large rocks to the center and made sure to compact
all the dirt with moisture so it has a solid base. When adding fillers such as I'm using here you'll
want to be careful and make sure you maintain an eight inch gap from all edges of the forms
so the concrete has good structure with thick walls. The next step will be adding a rebar cage
to the inside of the stair forms. Again I'm using some half inch rebar and I've bent three main
supports that match the shape of the stairs. When adding rebar to the inside of the forms
you'll want to make sure to maintain a one and a half inch gap from all edges and not allow the
dirt as well. So here's a look at the rebar cage. I have three main supports that match the shape of
the stairs along with vertical and horizontal supports every 12 inches. And in all the areas
where the rebar would have come in contact with the ground I've used pavers for the rebar to rest
on. So I got my rebar cage in place and I'm just about ready for concrete. But before I start
pouring I'm going to add some more side supports to the forms to keep them from bowing under the
extreme pressure caused by the weight of the concrete. For this I've added two by fours approximately
every two foot then secured them to the forms with screws. Then secured the opposite end of these two
by fours to the ground with form stakes. And this was done on both sides of these forms. Now it's
time to start pouring the concrete. For this I've ordered around two and a half yards of ready mixed
concrete. To figure out how much concrete you need there is various concrete calculators online to
figure out the math for you. This staircase requires about three yards of concrete but I did
add some filler to the middle of these forms earlier which was about half yard. So I ended up
at two and a half yards. As you can see here I've started pouring from the bottom step and will work
my way up one step at a time while making sure to pack the concrete thoroughly in all areas. I will
also be using a concrete vibrator which I'll be demonstrating here in just a few. The concrete
should be at a consistency where it's wet enough to pack and fill all areas but not so wet that it
starts spilling out of the bottom steps. It's very important to make sure the concrete is packing all
the way to the bottom of the forms. The higher you get on the stairs the harder it will become to pack.
That's where the concrete vibrator comes in handy. The vibrator helps the concrete settle to the
bottom and fill all voids but you have to be careful not to overuse the vibrator because this
can make all the rocks and the concrete mix sink to the bottom which will severely weaken the
concrete. So just a few seconds here and there should do the trick. And at this point here I'm
hand packing the outer edges of the forms to make sure the concrete fills around the steel H beams.
Now it's time to start adding more concrete to the top and I will continue to hand pack and use
the concrete vibrator with every one foot of concrete that gets poured. So right here I'm
getting pretty close to being done pouring the concrete. I just got one foot left and now it's
time to use the concrete vibrator one last time. Again being careful not to vibrate the concrete
too much because I don't want the rocks to settle all the way to the bottom. Now it's time to start
screening the concrete and remove any excess concrete. The objective here is to get the
concrete flush with the top of the forms and fill any low spots that may exist. And this will usually
require a couple passes. When screening I like to use a sawing motion. This helps cut the excess
away while filling the voids at the same time. After screening the concrete I can then start
floating the concrete which will start to give the concrete a much smoother appearance. After
floating all the concrete I then wait for the concrete to harden to the point where I can only
push the concrete down with my finger about one quarter of an inch. At this point I can begin
finishing and edging the concrete. If you plan on leaving the rise forms in place as I will be doing
you'll want to make sure the concrete is flush with the bottom of the rise forms. Otherwise
you'll end up with blemishes in the corner areas. Edging the exposed edges on the concrete
is highly recommended because it packs and strengthens the corners plus gives the steps
a nice rounded edge. After edging if you desire a broom finish now would be a good time to lightly
broom the steps. And if you plan on removing the rise forms to finish the areas behind it should be
safe at this point to remove these forms. But I will not be demonstrating this step in this video.
After waiting approximately 24 hours for the concrete to harden I can now begin to remove
the forms. And as long as the forms were greased properly they should all remove fairly easy.
So I will start first with removing the rise forms. And here's a look at it after removing all
those. And now I'm going to go ahead and remove the OSB forms on these sides. So as I mentioned
earlier I chose to use OSB because I like the texture it leaves in the concrete. But others may
prefer to use just regular plywood. And here's another idea if you wanted a different texture
you could use sheets of T111 siding to get a siding looking finish. And here is a look at
the concrete steps after removing all the forms. From this point these steps are ready to use
but we still did a little more work. The next step was adding some custom rebar railing
and some decorative angle iron on the corners of the steps. Then we removed approximately four
inches of dirt around the perimeter of the house. Then added some concrete slabs that surround the
steps. Okay it's now time for me to go. Hopefully this video will help you out with your concrete
stair project. Have yourself a great day and I'll see you next time. Oh and if you like this video
if you could hit that like button.