Application of Soil Mechanics by Dr. Nihar Ranjan Patra,Department of Civil Engineering,IIT Kanpur.For more details on NPTEL visit http://nptel.ac.in
So, we have finished last class positive projecting conduits. In this case, one thing will continue
that is your plane of equal settlement. When a high field exist over a conduits that means
what do you mean by plane of equal settlement. If I say that means when a high field high
field exist over the conduits, then the settlements are more in the top. It is more on top and
progressively decreases you can say that progressively decreases top of here top of conduit you can
say that progressively decreases towards top of the embankment. At certain height h e above
the conduit, you can say that at certain height h e above the conduits, a horizontal plane
exist a horizontal plane exist at which differential settlement is zero at which differential settlement
is zero differential settlement is zero. This plane called plane of equal settlement
this plane is called plane of equal settlement plane of equal settlement above the plane
of equal settlement central zone this side zone settles equally. If I draw it if I draw
it diagrammically in figure a positive conduits with this this plane is called plane of plane
of equal settlement. This is your top of embankment top of embankment, and this height is known
as h e, and total height is your capital h, and this is called this is called your
critical plane. If you look at the definition plane of equal settlement that means when
a high field exist over the conduits that means the field of height of the field is
very high. So, that over burden pressure will be more this is called a when a high
field exist over the conduits, and in this case what will happen exactly the settlement
is more on top of the conduit. Look at here the settlement will is more at the top of
the conduits, and what will happen the settlement will be progressively decrease the settlement
will progressively decrease as we proceed from top of the conduits.
This is your conduit top of the conduit to your top of the embankment condition one there
is a high field there is a high field. So, once there is a high field what will happen
the settlement above the top of the conduits will be very high, and this settlement will
be slowly slowly it will decrease slowly slowly it will decrease it will decrease what happen
at certain point at certain point there is an horizontal plane exist there is a horizontal
plane exist at which the differential settlement is zero differential settlement is zero this
plane is called plane of equal settlement. That means plane of equal settlement means
the settlement here here here everywhere else around, and above the top of the conduits
will be equal whatever it settle will be equal this is called plane of equal settlement.
So that means h is your height below your equal plane of equal settlement to your conduit
top surface h is your total height below which from the top of the embankment where the where
the conduits is there. So, why you are interested for this plane of this plane of the equal
settlement or plane of equal settlement line if you see type of positive projecting conduits
if I write it type of positive projecting conduits for a complete these conduits complete
these conduits h is less than equal to h c h is less than equal to h e h is less than
equal to h e. So, r p is equal to negative, then complete projection conduit complete
projection conduit in this case in this case sorry for complete these conduit h is less
than equal to h c for complete projecting conduits h is less than h e in this case r
p is equal to positive, then incomplete these conduits incomplete these conduits incomplete
these conduits in this case h is greater than h e where r p is equal to negative, then incomplete
projection conduits incomplete projection conduits in this case h is again greater than
h e where r p is equal to r p is equal to positive. So, these are the all classification
based on your plane of equal settlement from this, because once the moment you identify
your plane of equal settlement, then you know your h e height above the conduit that
is your h e that is called plane of equal settlement, and depending upon h e is greater
than h or h is greater than h e it should be classified as it should be classified as
complete these conduit h is less than h e complete projection conduit h is less than
h e r p is negative or r p is positive, then incomplete these d i t c h incomplete these
conduit r p is negative, then incomplete projecting projection conduit r p is positive it depends
upon that how h and h e are there. So, some relationship has been given by some
relationship have been given by for this positive conduits plane of equal settlements by this
author this is m a r s t o n maston has given the following expression for positive projecting
conduits in this case gamma b c square c p where c p is your c p is equal to coefficient
coefficient this is equal to e plus minus two k mu prime h by b c minus one divided
by plus minus two k mu prime this is for your positive conduit this is for your expression
for positive projecting conduits similarly for incomplete conduits similarly for incomplete
conduits your c p comes out to be c p is your e plus minus two k mu prime h e by b c minus
one divided by plus minus two k mu prime plus h by b c minus h e by b c into e to the
power plus minus k mu prime h e by b c. So, these are the two relations based on your
plane of equal settlement maston has given for positive projecting conduits, and incomplete
conduits now next part of this we are going to start that is your negative projecting
conduits of your complete derivation as well as a theory behind it.
So negative as I said earlier these positive conduits negative conduits as well as imperfect
conduits the definition has been explained by diagrammatically. So, we will start this
negative projecting conduits case now first case is over for positive projecting conduits
now second one is your negative projecting conduits if I draw a diagrammatically how
it looks it has been used for culverts example for culverts. So, this is your top of embankment
this is your plane of equal settlement plane of equal settlement, then if I start with
this negative projecting conduits below this top of the embankment there is a culvert,
and drawing this how it works slightly increasing diagrammatically let me put it in this way
this is your delta g p b d, and this part will be rho d plus sorry delta d plus delta
f plus delta g, and this is your critical plane critical plane, and this is your critical
plane after settlement, and if I take it this two this is your kind of d c b c b d, and
this part will be overcoming delta f. So, as I said in case of negative projecting
conduits r p comes out to be delta g minus delta d plus delta f plus delta c by delta
d. So, where delta g is equal to settlement of ground surface delta d is equal to settlement
of backfill in trench delta f is equal to settlement of conduit foundation d c is equal
to vertical deflection d c is equal to vertical deflection vertical deflection of conduit.
So, as usual it is weight w c is equal to gamma for negative case b d square into c
n c n is your c n is your coefficient of negative projecting conduits c n is equal
to coefficient of negative projecting conduit, and c n comes out to be e to the power minus
two k mu prime h by b d minus one divided by minus two k mu prime when h is equal to
less than h e, and this will be with the same term same term plus h by b d minus h
e by b d e to the power minus two k mu when h is greater than h e if you look at this
negative projecting conduits where it has been used negative projecting conduits example
is a culvert. So, there is a culvert here I have drawn the culvert there is a culvert
here in this culvert this conduits is there above this is your top of the embankment top
of the embankment that means filling part is there.
So, if I draw this if you look at here one is your plane of equal settlement one is called
plane of equal settlement it will be below your top of embankment. So, that means up
to from plane of equal settlement to top of the embankment whatever the settlement is
going to happen it should be equal it should be equal. Now the settlement below this if
you look at here there are things like critical plane this is your critical plane, then this
is your critical plane after settlement there are particularly four type of settlement observed
delta g if you look at here delta g settlement of ground surface the ground surface in this
particularly conduit at this level. So, this has been settled with this your dotted line
because what will happen once there is a conduit try to understand once there is a conduit above
this there is a filling material what will happen the conduit also settle, then the material above
the conduit also it will also settle along with side by soil also it will settle.
So, in this case delta g is your settlement of ground surface that means it is nothing
to with this it is only the ground surface how much amount it settle it is your delta g,
then delta d is your settlement of backfill in trench where is your delta d if you come back
here delta d delta d is your settlement of backfill in the trench that means whatever backfill you
have done particularly above the trench because this is a trench this is your trench above the
trench. So, that is your delta d settlement of backfill in the trench, and delta f is your
settlement of conduit foundation if you look at here conduit is resting over the pressure of the
soil what will happen the conduit also settle the conduit settle where below this there is also soil.
So, conduit settlement of conduit foundation this is called below this called conduit foundation.
So, this part is from here to here it is called delta f that means this is your conduit settlement
d c is your vertical deflection of conduit if you come back to your d c at the top part how much it
will because once the conduit will settle at the top conduit will settle at the bottom at the top
what will happen this is we called a vertical deflection of conduit the conduit will be
deflected some part of vertical deflection. Then at the bottom conduit will settle at the
bottom conduit will settle because here there is a soil here below the conduit there is no soil
this is a water pipes or may be something it is a concrete. So, this is called deflection here we
are calling at a settlement. So, there are four type of settlements one is your settlement
due to your ground surface, because of your ground surface. Then second is your settlement
of backfill in the trench third is your settlement of conduit foundation this is your conduit
foundation fourth is your vertical deflection of conduit fourth is your vertical deflection
of this conduit this is your vertical deflection of the conduit. And now with this is complete
how the settlement of conduit how the settlement of foundation soil how the settlement of
particularly your kind of ground surface all if you look at here conduit settles above the conduit
soil settle below the conduit what will happen ground surface settle, and below the conduit
also foundation also settle. So, everything has been taken into consideration based on that
as I said r p r p is your delta g minus delta d plus delta f plus delta c by delta d.
So, based on that based on that the w c is coming about gamma b d square into c n c n is your
coefficient of negative projecting conduits c n is your coefficient of negative projecting conduits
in this case c n comes out to be this term once h is less than equal to h e where is your h e
as I said h e is your distance of the conduit distance of the conduit above the conduit to
your plane of equal settlement this is my plane of equal settlement this part is your this is your
h e now what is your h h is your from here to top of the embankment this is your h now as I said
when this plane of equal settlement you are going to observe if this height above the conduit is
more high that means filling material is more high. So, it will be in that case you are going
to get plane of equal settlement that is the condition otherwise you will not you may not
get your plane of equal settlement. So, these two terms depending upon that you can say that if
h is less than a h e what is the c n coefficient of negative projecting conduits if h is greater
than h e what is the coefficient of negative projecting conduits. So, these are all about
this how how it settle how the behavior will settle what will happen what will happen in
this case what will happen the settlement will be kind of this kind of settlement this kind of
settlement it will go all of sudden it become a plane plane of equal settlement plane of equal
settlement means the settlement at the ground surface settlement above the conduit settlement
of conduit settlement of foundation surface settlement of ground surface all will be equal
all will be equal all will be suppose it is suppose somebody say if it is a ten m m of
settlement at the plane of equal settlement that means delta g is equal to ten m m delta
d is equal to ten m m delta f is equal to ten m m delta c is equal to ten m m.
So, this is called plane of equal settlement. So, how this in this case negative projecting
conduits what are the what are the effect how the effect has come it has been completely drawn in a
figure where b c is equal to b c is equal to diameter of conduit b d is equal to width of
your trench width of a trench, because this is your culvert this is your culvert width of trench
where trench has been made, then culvert has to be erected. So, this is your b d is equal to this.
So, this is all about your negative projecting conduits may be next class we will start about
some special conduit cases of the complete derivations. Thanks a lot.