Public workshop over Auburndale data center

Fox - 13 News
14 followers
Nov 11, 2026
AI Generated·May contain errors
Proposed hyperscale data center in Polk County
is generating a lot of attention tonight.
A lot of attention, so much
so that more than a thousand people showed up,
a thousand at this public workshop in Auburndale.
They had to have it at the Civic Center there.
This project could bring hundreds of jobs, about 300 permanent jobs,
but it would also require an enormous amount of electricity
and residents want answers about what
else it could mean for their community.
Fox 13's Jennifer Vagelis is outside the Auburndale Civic Center
to break down the details of what would be called
The Auburndale Technology Center.
Tonight, we heard from city reps, the developer,
and Tico about what this data center would require
and what it would bring.
But many residents stepped up to the podium,
begging the city to reconsider.
And if you don't have the backbone to stand up to them,
we'll take your place.
Several hundred people packed
into the Auburndale Civic Center Tuesday night,
all with questions about the proposed Auburndale Technology Center
that would sit on 75 acres along Pace Road.
You know, people put their whole life savings
into property and home ownership,
and you have a data center that's coming in.
Automatically, you drop down by 10%.
In December 2023, Auburndale City Commissioners approved
a new land use designation and rezoning for this property,
allowing industrial and certain technology uses,
including a data center.
Construction on the first two
of four approved buildings started in early 2024.
It was then purchased in December 2025 by Pace Road DC Development.
Some of the commissioners serving
acknowledged they weren't in awe of the
office when that decision was made.
Had it come before me, I don't think at the time
anybody was anticipating a data center.
I will not allow a rubber stamp process
to jeopardize our resources, our economy, or the peace of our schools.
Tico would supply the power with demand expected to start
at 350 megawatts and eventually increase to 700 megawatts.
That's enough electricity to power 350,000 to 500,000 homes.
The developer estimates the facility will use more than 4600 gallons
of potable water a day using a closed loop cooling system.
And noise at the property line would be limited to 50 decibels,
about the level of a quiet office.
The Auburndale Technology Center is different.
We designed this intentionally
to address concerns
that other data center projects have raised throughout the country.
The developer is also promising an economic boost,
projecting 292 permanent jobs and says
the project will not receive financial incentives.
The first two buildings are expected to be
operational by 2029.
But even with those promised benefits, there are still big questions.
Do we have the capacity available to oversee a project like this?
It's not a done deal.
On November 4, the developer submitted a building permit
application and I
Interior retrofit site plan,
which the city still needs to review
as for who will fit the bill for
all those electricity costs.
Florida Senate Bill 484 was signed
into law earlier this year that
would require data centers to foot
the bill for all electricity and
infrastructure costs, but Tico still
needs to get its new tariff approved
by the Public Service Commission in
Auburndale. Jennifer Vegas Fox 13 news.