DAY 13 | Framing a house Start to Finish | Framing Walls

Dave Does Carpentry
1 follower
3 Video Views·Nov 18, 2026
In this video we mark our the plates for the upstairs walls, and we manage to frame and stand the majority of the walls
AI Generated·May contain errors
Video Summary
AI GeneratedThe video demonstrates the process of marking out and framing the upstairs walls of a construction project. The team follows architectural plans to precisely position windows, studs, and load-bearing beams, ensuring structural integrity and alignment before standing the walls and preparing for truss installation.
We are back in the frame and I'm going
to jump straight upstairs to finish a cutting and today
we want to mark out all the walls
and hopefully get them all framed and standing by this afternoon.
All right so marking out these walls are actually going
to be a little bit easier than downstairs
because none of the windows have been measured yet.
Downstairs they were all made and they were
a little bit different to the plan.
This means we can follow exactly what's on the plan and
And they'll be correct.
So this window, we're going in 690, 690 either way.
from the cladding.
Our total wall size, including cladding, is 190.
So if you hold 190 on your internal junction
and then mark 690,
let's do a tiny tick, yep,
because that mark is accurate window.
We wanna make a window opening 10 mil bigger,
so mark across 10 mil.
Can you hold my tape?
Our window is three metres,
so this should be 3020.
I've got three metres 10, which is perfect,
because I'm gonna go 10 mil as well.
Sweet, and square that across
and I'll work out what beam we've got.
And you can add in any studs you need before that too.
That's downstairs, upstairs.
It's a triple stud.
So that's one cross.
It's for all of our studs.
It wants one checkout.
And then we'll have two closes.
Actually, I completely forgot what I was doing.
I think you followed me.
We'll leave that for now.
But normally, I think we did this downstairs.
I'll do a W for the checkout and crosses for the closes.
This is RL5.
RL5 is a double 190 pine.
Do you mind writing that down, please?
And this is a 3020 by 2420 opening.
That's good, we might make our way
down this main wall here then.
This entire wall though is just, yeah,
just normal the whole way through.
So we've got no window until we make it to the ensuite.
So if you wanna do 450s through there,
actually I'll hold your tape for you.
Do you wanna quickly mark through?
Just do a, what I'll do is just go through
and do a quick little tick, yep,
and then we'll square those
and you can mark the studs afterwards.
I'm just gonna square them and meet you in the middle.
Actually, I'll square these through.
Do you want to start doing 450s in that next room
that you're in?
And then we've got a stud there and we've got a stud here.
All right, so for the en suite,
we've got a 1210 by 400 window.
So we'll go 1230 wide by 420 high.
This window, Mitch, is just centered in the room.
From the plan, I can see that's 1800.
It's an 1800 room.
So did I mark 12, I didn't mark 1230.
Um...
Yeah sure we can do it that way,
yeah so mark 900 and then window is going to be 1230 so you want
615. Sorry I should let you do it mate you're all over it.
12 what? 30. And that's our frame opening
so you can square that straight away.
And for the engineering, for the engineering double study the
side so yeah we'll do the window and the cross.
I think that's a little bit neater and it's an RL4.
An RL4 is a 140 pine. I think I'm marking the bottom plate here, yeah.
So we're at 140.
Next time when we open walls up,
we want to flip them the other way.
Because this is a top plate that we've been nailed to.
Oh, yeah.
And we marked squared L junctions in the top.
That's okay.
I'm marking this side here, we'll make that the top plate,
so that when we frame it, we can open it up here
and then stand it straight up.
While we're here, we'll just keep going around
with these internal walls.
So this one isn't a wall going the entire way.
We've actually got two walls that stop there
and we've got a wide opening, no header or anything.
I want to frame it, we can cut the bottom out
but I want the top to go the whole way through just to
hold everything and plumb in the right place.
So you come in 900, mark 900 and then it's going to
be an 800 opening. So for that 800 I reckon we
um cut off the bottom plates before we open this
wall up and then um just do a note on the top plate saying
no headers cut out. I'll just write
That's right, cut out later.
Can you go through, just mark four 50s there.
This one.
1150 by 450 niche, yeah that's right.
So what I think we might have to do is we're at a 190
lintel in here to over engineer it
because this is going to be a load bearing wall. So I'm just
going to do a W even though it's sort
of window just so when we see that we know
we've got a load stud there.
I'll do the same thing here we'll come in 90
window and across. So we've got a slider in here
and the slider or the jam of the end
of the slider wants to match up with that there.
So for that you did 900 and 800.
So I'll get you to mark 1,700 and maybe go 1,710.
It's 820 CSD in there.
Yeah, there's 300 and then I've added another stud just up here.
Nice, I like that.
Can we make that a double stud?
I think that should be fine, but we are going
to put another bit of James Hardy going up
there for the underlay for the waterproofing.
And then we'll have a toilet there as well.
So that potentially can get packed out close to 40 mil.
So we'll have a stud there and there,
and they're probably gonna more than likely
screw the shower screen into that.
Good thinking, Mitch.
Looks like it's really good.
Oh, one thing I'm glad I just checked.
We're gonna change this here
because our toilet is actually going around there.
And we need those 500 openings
because the toilets can be inbuilt
in the wall toilet system.
So what we will do instead
is I'm gonna make this window
Span over there and we'll get rid of that and that's a 190 or 140.
We're adding another 300 mil
I'm going to change that to a 190 pine which should be over the top
But we will always check with the engineer every time we
change something like that. That's good what you've done there
This wall here is a normal wall
Um, normal wall.
Yep, so just do your
350s and that same thing you've done there
to mark out for the shower screen
That's nice. And this is all a normal wall through here externally.
So I'm just gonna run through and do this
And then the boys have marked out the rest of it,
so we'll
be standing mules
in half a second.
Studs look pretty good.
This is looking good, Mitchie.
I might jump on the gun.
Do you want to mix it up?
Normally, I've got you on the gun and I'm cutting for you.
I might jump the gun.
Do you want to have a go trying to cut?
Do the checkouts, put the beams in.
A window height everywhere, 2-4-20, okay?
2-4-20, and then obviously you come down for 2-4-20,
whatever
that
window
height
is marked.
But this is long enough.
We'll
find
out in
a sec.
You got
inner
mill?
A wall there with the side opening, that goes here,
So whoever does these two cross braces on these walls,
make sure you do them on these outsides
away from the bathroom.
These are the hollow sides of the studs too,
and then that way we don't have the cross brace
in
the
bathrooms.
Got a wall there that we haven't laid out yet,
and once we pull those walls over,
it's gonna get trapped in place.
Let's get these two done, stand them up,
and then once they're stood up,
we can pull this wall open, frame that,
and
stand
that up
straight
away.
Now, to make sure you're happy to shoot the tops,
I'm just gonna plumb up
that stair board.
Let's go on.
Let's just go that way,
and we'll just slide it across,
so you don't have
to step down.
All right, we had a pretty good push today,
apart from the rain that kept hitting us
towards the end of the day.
So I did put the camera away for most of that.
So we got most of this side of the frame done,
or actually all of that side of the frame done.
We're gonna have to come back later
and frame a wall returning in that way.
That's all open glass balustrades there,
glass balustrades around there,
and a glass balustrade there.
So that side of the house is done.
The trusses are gonna be spanning
all the way over to a wall there though, so.
When we get here on Monday next week,
we're going to have to go through with some S17 studs,
put a few more beams in there, build that wall up and finish that up.
And the same thing over here.
I need to look into the detail.
I don't know if we've got F17 studs going up here or not,
but we do need to get all the beams up
and pitching plates up on top of that
so that our trusses can span over and finish in that wall.