Manitoba Hydro overestimated demand for electricity: regulator
Nov 25, 2026
AI Generated·May contain errors
Video Summary
AI GeneratedThe Provincial Energy Regulator has recommended that Manitoba Hydro scale back its planned expansion of a natural gas plant in Brandon. Instead of adding 750 megawatts via three turbines at a cost of $3 billion, the regulator suggests adding only one 250-megawatt turbine, citing overestimated electricity demand and the need for more affordable, sustainable alternatives.
Manitoba Hydro wanted to expand the generating capacity
of this natural gas-burning plant in Brandon by 750 megawatts.
Hydro wanted to add three turbines at a cost of $3 billion.
In a 223-page report made public Wednesday, the Provincial
Energy Regulator says Manitoba doesn't need this much power
and recommends Hydro only add a single 250-megawatt turbine instead.
Premier Wabkewick says this is good news.
We're on a track that's probably more
affordable, better for the environment,
but still going to work in terms of keeping
the lights on and the houses warm in the wintertime.
The report from the Public Utilities Board went further, though.
It says hydro overestimated the demand for electricity,
both by misjudging how fast the economy is going to grow,
and by assuming electrification incentives
that don't even exist right now will have a big effect on demand.
The PUB recommends the province set hard targets for saving electricity
and build up 100 megawatts
of battery storage instead of a 5 megawatts hydro plant to build.
Critics say the report is good news for consumers
and an important lesson for Manitoba Hydro.
If they would have been investing
in 750 megawatts of natural gas turbines,
that would have closed the door to other alternatives
that might be more cost-effective a few years down the line.
Manitoba's climate action team says the province
also deserves some of the blame for jumping the gun.
It basically announced the 750 megawatt.
Gas plant in its 2025 throne speech,
it came out of nowhere and it was announced as if it had basically
been a done deal prior to the PEB even having a chance to look at it.
Manitoba Hydro says it will not comment today.
The Premier says he'll give Hydro until January to respond and then
will determine what direction the province gives the Crown Corporation.
Barbara Kivas, CBC News, Winnipeg.