Bathroom Remodel Bathtub to Curbless Walk In Shower Time Lapse

ZEM Construction
5 followers
30 Video Views·Nov 3, 2022
Hey guys, Zach here with Zim Construction bringing you another remodeled project.
In this video I'm going to show you from beginning to end a bathroom that we recently finished up.
I just want to start off by saying thank you to everyone who left me some feedback about
narrating versus just letting the time lapse play out. Overwhelmingly you guys enjoyed the
narration and me talking through the project so I'm going to do that this time. The goals
for this bathroom were to have it be a shower wheelchair accessible bathroom.
The story is quite heartwarming. The client of mine is doing this all for her mother who lives
with her. They really want to give the mother as much independence as possible and by allowing her
to be able to shower independently is a huge step in that direction. So the design for this
bathroom came completely from the client. I had very little input. She had a lot of goals that
she really wanted to accomplish and I wanted to do my best to help her achieve those.
So the first step in doing a wheelchair accessible bathroom is the zero entry
shower so that a wheelchair shower wheelchair can just roll directly in there. So in order
to do a zero entry the drain must be the lowest point and so in order to get that I actually had
to cut out the existing subfloor embracing and create blocking so that I can lower that section
of the floor. As you can see here I'm adding some two by fours reinforced allowing the first
layer of the subfloor to be put in as low as possible. It's quite unfortunate during the
process of this they only have one bathroom on their property and so for the last three months
they've had a porta potty on the outside of their house in the driveway. So just imagine what they
had to go through in order to do this project. She was hoping to get this project done by herself
and had several people that were going to help her out and all those contacts ended up falling
through unfortunately and it got to the point where she needed to bring in someone and get it
done as quick as possible because the three to four month time period was just not working for
them. So here I am putting in some more of the subfloor cut out individual slats and of course
everything is glued and screwed down very securely. We also included a small bench that
was more used as an accessory platform or a small shelf. It was only seven inches wide we wanted to
leave as much space for the shower wheelchair to be able to go in there and roll around.
We wanted to do a big dividing wall because of course no door in this we didn't want anything
that would obstruct the shower wheelchair to roll in there. So here we are putting in the
half wall reinforced to all the studs and joists. One of the main design elements that my client
wanted to add was the glass blocks. So there's several different places we included these glass
blocks as you will see here in a little bit but in this case the best route to take was we actually
made the glass block windows separately to then be installed later around these frames. So
since they weren't being put in place it allowed us to get all the way around them make sure every
part was sealed and done properly. It was really nice because after this was all dry
the install went super fast it was almost like adding traditional windows. Here's also a great
shot of the porta potty in the driveway that they had been using for the last several months.
All these things actually were purchased from Lowe's and throughout the project almost all of
the materials were already purchased also. So she had all the tile everything all the blocks ready
to go for us which was great. You know there were a couple adjustments I had to make just so I could
use materials that I'm more familiar and comfortable with. So the three places that we actually
included blocks is one in this dividing wall and then another place was here in this old window.
We actually removed the old window completely redid all the framing to include those glass
blocks as well as included a small shampoo shower niche. So here I am adding some of the framing
in order to put the glass block window in. We of course went from the outside and made sure
everything was sealed and insulated and cleared. The third spot you will see here is actually in
the exterior wall above the main door in the bathroom. So here we are adding some blocking
around the shower pan so that the pan liner does not just fall into the walls has a place to be
secured to and and waterproofed. And of course after the pre-slope we added a pan liner.
This was attached all the way around and of course glued to the three piece drain that we used.
We also added cement board on the floor and here I am mixing up the dry pack mud for the
shower pan. The mud got a little bit wetter than I wanted to but it all actually worked out great
in the end making sure to add that quarter inch per foot of slope to 4-pop drainage.
One of the design elements that the client really wanted to include over the shower niches
we added one underneath the blocking in the window as well as another one on the half wall.
She really liked the arch look with tile which added for quite a bit of intricate tile work but
in the end it turned out great. Here we are adding all of the Durrock cement board. A huge design
piece that she really loved that she's seen on some of her travels around the world was
the floor to ceiling tile look. So the entire bathroom is going to be covered
in tile from floor to ceiling all four walls even up and around the door.
As you can see we're putting all that stuff in and those of you eagle-eyed viewers will notice we
forgot to add insulation back in on this interior wall but don't worry
we went back and took those off and added the insulation back in there.
Gluing in the shower niche. Here's a quick shot of us finishing up that insulation and
reinstalling that cement board. Doing some last minute Durrock work around everything.
She had purchased so much Durrock that we didn't end up needing to use anything else it was just
at that point we had plenty so we ended up just keep using that. And of course after the Durrock
was all installed we added the mesh tape around all the joints and then used a quick drying thinset
as a barrier for sealing up all of those seams and joints.
A couple pictures of where we were at. She was getting very excited this is one of the
most rewarding projects ever just from where everything was going and how things had started
and the difficulties that she had run into all the way through to the finished project every
single day she was so excited i mean there are tears and laughs and joy and it was it was so
rewarding to work with someone who's so appreciative it was such a joy working with this with this
client in particular of course she made us cookies and lunch and and zucchini bread fresh from the
garden and what an incredible experience so it was really really rewarding to have her see each step
of the process and what was involved so of course we left a gap between the bottom of the shower pan
or the top of the shower pan and the bottom of the cement board i'm not going to go into too much
detail about how to waterproof a shower there's content all over youtube on right and wrong ways
to do that i will tag some of those good youtubers in the description below if you have any other
questions so the process we went with was the durock and red guard red guard is a product you
can purchase from home depot works great all of the joints and corners got three coats brushed on
all of the surfaces actually get rolled on in two coats on that and it's quite easy to install
pretty straightforward it's very very similar to painting except you do not need to be as precise
it is all going to get covered up as you can see here it painted on the first coat of all
the joints and then i go back and roll everything on and then just continue the process until
each spot has their desired here is the last coat all finished up and looks quite pink but
what's great about this project or product is that you know exactly when it's dry
as it turns a dark deep red as you can see right here so what's great about red guard is when it's
finished and dried you could actually shower right now as is completely waterproof the tile
at this point is just a great way to divert some of that water and of course it looks nice and
and adds for the longevity of the of the shower so we're starting with the main wall on the right
side as well as some of the more intricate details along the shower niche i'm using some
thin plywood as spacers to hold that section of the tile up while the thinset can dry underneath it
all of the borders around all the windows and tile niches had a
bullnose round over which has its pros and cons but in this case it turned out really nice
of course both sides of the dividing wall had a little window to cut out i also used some screws
to hold up some of the bottom pieces of those outlines and of course went back and caulked all
the screw holes we are moving our way around the entire bathroom the floor was not perfectly
regular throughout the entire bathroom so what we did was did a perfect level line of a cleat
all the way around and then installed the tile on that cleat and then went back and added the
bottom row very last so here we are in the shower putting on some more of the tile we did the entire
bottom section first and then we have a decorative mosaic tile that goes in one continuous stripe
all the way around the bathroom and also inside the shower niches one of the main design elements
that she really wanted to include was the shower niches also lined up with that main stripe as you
will see here but that the stripe went perfectly through the center of the shower niches which
caused for some grout lines to be in some different spots but overall it turned out
great i am working on the outside of the dividing wall pretty small and tricky pieces
try to make everything look great each grout line is lined up perfectly you might be able to see on
the right side of the screen a green laser line it is one of the most crucial tools in my opinion
on making sure that all your tiles are straight and lined up and level grout lines match up
by having this tool makes it so much easier you can set your first row and then line up the laser
on the grout line that you want to match up and then every row after that has a great starting
point of course every single tile in the bathroom is back buttered which that means the thin set
is applied to the wall as well as a small thin layer tied to the back of the tile so that when
they are pressed together there's complete coverage all the way around after the first
several rows had some time to dry now i'm going through and adding the mosaic stripe process it's
pretty nice each piece lines up with the one previous so work work your way around cut around
the corners and the stripe needs some time to dry to go through and add the other arch around the
process that we decided to go with was by dividing the long stripe up into five small sections
this worked great and allowed for integration of the rest of the tile
super nice shots a little out of focus unfortunately but here we are starting the
other section of tile above the mosaic stripe this is where the laser comes in really handy and
once you get your first row set up then our column i should say each once the first column is set up
it makes the rest of the process super easy because the each one lines up with the one previous and
all of the grout lines throughout are lined up of course i used a tile leveling system
the houses in our area are old and have moved and shifted and warped and so all the walls are
not perfectly straight so adding this leveling system makes our lives so much easier so one of
the main features is that they did not want to include a vanity or sink actually in the bathroom
itself she wished to have that section in the closet outside so that she her mother could
roll her wheelchair right underneath brush her teeth wash her hands do all those things
separately without impeding in the space in the small bathroom we didn't get the finished countertop
process but he was pretty proud of his work and was demonstrating the strength of it now here we
are lining up the tile that we placed in later and drilling out the hole for the sink and the faucet
she also included a new exhaust fan as one of those great ones that just looks like a recessed
light but actually has room for air to move around the light bulb itself great little product and
added to the elegance of the bathroom as you saw earlier in that closet all of the plumbing was
done previously before we had ever showed up so that made it made our jobs really nice
but even moving around that window and some of the more complicated areas was still crucial that we
kept all the grout lines lined up again you can see that green light for with the laser
and also another challenge that came along with this step in the process was making sure that
the tile from one side of the dividing wall lined up perfectly with the other side and you can see
there i actually miscut a piece and had to kind of recut it made an archway as you can see right
there that that tile unfortunately the camera stopped recording at that point to finish up
this wall but i really wanted to highlight that one of my favorite parts was around all those
glass block niches in the above the doorway so because there was so much surface area and so
much grouting to do we actually started some of the grouting process while i one of us was setting
the rest of the tile so one of us is grouting while the other one is finishing up the
dividing wall with the bullnose along the side and the top the other one is going through prepping
for grout and starting to grout some of those cleaning out those joints making sure all of
the spacers are pulled out almost all of the tile besides the bullnose and the mosaic stripe
were a 12 by 24 inch tile even the tiles along the floor the floor had a different pattern
as you will see here in a little while so after all of the tile along the walls was finished up
you can see that cleat next we went to the floor so the way i like to do bathrooms is having the
floor tile actually go underneath the wall tile so the wall tile is sitting above the floor tile
so any water that does hit the wall and drip down will then just drip straight down to the floor
and go right into the drain as opposed to going down in between the floor tile and the wall itself
one of the main goals in building this bathroom was that when the house ever gets to be sold or
the design needs to be changed to not necessarily allow for just wheelchair accessibility was we
wanted to design it so we can make those changes so eventually someday we could easily add a glass
door to this shower and as well bring in the the sink and vanity back into where they would
traditionally go all of those things would be it would be fairly easy to get done so here i am
putting in the pebble shower floor pebbles are great minimal cutting have a couple spare sheets
and you can literally just cut out the ones that you don't want and insert the small pieces and
small rocks where you need to go the goal is to try to make as few cuts as possible to make it
look natural at all of the the pieces were meant to go there so at first i did a quick layout of
where i wanted everything to go and removed everything and brought each section in piece
by piece to ensure perfect coverage and alignment throughout the entire floor again there are some
design elements here that we wanted to keep of course by the shower we needed to have the uh that
direct cement board on the floor but the client wished to have the transition between the hardwood
on the outside of the bathroom and the bathroom tile itself to be as small as possible so we did
not add that cement board throughout the entire floor and added a little bit of a ramp as we
continue grouting i one of us is adding the final bottom row to the rest of the tile this was a lot
of surface area a lot to be grouted another design element that we wanted to keep consistent was the
grout color so the same grout color is throughout the entire bathroom so the tile floor the walls
the mosaic and the pebble shower floor so the client picked a color that she felt worked well
with all of those i think she made a great choice and it looked looked great we added some grout to
the outside of the pebble floor so that the wall of the shower could be put on top again like i
mentioned before any water that does drip down the wall will hit that tile floor and then hopefully
work its way to the drain as opposed to seeping its way up underneath working my way out of the
shower and around i was back buttered like i said before the floor was not perfectly level and flat
so these pieces were quite custom in order to fit along these ebbs and flows of the floor but also
to look nice and finish up that grout line along the pieces that go above it we drilled out a nice
hole for the toilet water supply to try to make that as seamless as possible again one of the
great tools to use when adding in intricate tile pieces like this is you put the tile backwards and
mark each side then when you bring in the tile after it's been cut it lines up perfectly by
flipping the tile over again there's videos all over youtube showing this process and the benefits
of doing it that way here we are now that all of the tile is finally set we are going through and
getting everything routed up and getting ready to be finished of course after all of the grout was
done and dried we went back with a sealer the 511 impregnator works great so another aspect of the
job was finishing up the trim work around what used to be a closet but now is the sink vanity area
added some casing around that doorway and doing some door trim while one of us is finishing up
grouting that countertop one of the main aspects that i was asked not to complete was any of the
painting so the client really enjoyed painting and that was something that did not need to be
done in order to make the bathroom accessible so once we were finished she was able to get
all the paint and everything she needed i did help as much as i could with guidance and
and in preparation here i am adding some nice trim detail around each of those blocks that
were included above the door we tried to get a trim that matched the trim around the rest of the house
very simple curved curve design and as we're getting finished up here i am setting the sink
she wanted a vessel sink type setup this works great for her mother she has full use of her
right hand so we did everything we could to keep light switches and the faucets on the right side
so that she could use those independently there's a lot of measuring and designing that went into
this and and here is the finished product of course i mentioned the paint is going to be
so the sink pours right in there makes it really nice her mom can just lean right over brush her
teeth wash you know what she needs to get everything done and of course there's a
handicap accessible toilet but here is what the customer saw on the final walkthrough
it was so rewarding for the customers they were actually outside and so excited to hear that
sound they had been almost four months now without a usable toilet on their property and so
to be able to use a toilet is you know one of those things we take for granted but they were so
so excited the shower handle everything was all installed testing it out as you can see there
there's a little bench we use some of the same floor tile for the top of the bench the niche
block wall all the way around the wood look floor and then they're going to add a shelf
or an armoire type scenario there so that they could do you know their morning routines and
things like that this project was ridiculously fun quite challenging there were some new
new aspects to the job and overall it turned out great the client was ecstatic they were
using it as soon as the grout sealer was dry and they're just beyond ecstatic i was so grateful
to be able to be a part of this project and and help them out and get this thing finished
the design turned out great i have to say the client had a great eye and and working together
with her throughout the design process was great very rewarding to see all of her ideas and design
come to fruition it turned out clean straight but had that warm warm spanish feel is kind of
what she was going for i think worked great so i just want to thank you so much for watching this
video and if you guys have any comments or questions or feedback i'd greatly appreciate
it if you left those down in the comments section below if you enjoyed this video i
would really appreciate it if you hit that like button and if you want to see more videos like
this and project time lapses i have several kitchens bathrooms and basements coming up so
if you would please hit that subscribe button and also i post as videos as often as i can
remodels only can go so quickly so if you wouldn't mind hitting that little bell so that when i do
post you get that notification thanks so much again i really appreciate you guys taking the
time to watch