Hello and welcome to this
course
in Lecture 11 of Principles of Management Under Maksh Initiative of Government of India.
Our focus today will be on the
change in value of money over time. Time Value of
Money. Let us remind you that the course The modules in
which we are discussing are
shown here and today we will start discussing a new module
i.e. Construction
Economics
so let us first see
how the cash flow happens at different stages of any project. How is the flow of cash?
First of all,
understand that below this axis we have
plotted negative cash flow i.e.
expenditure. Positive cash flow has been plotted above
that is revenue. Now if we
talk about different stages, then the most First there is planning,
then there is construction and finally the
operation and maintenance phase which is a
very long time of 15 years, 20 years, 25 years.
Construction usually ends in two to four to five years.
Whatever time it takes for planning, it will take if we consider the cost. According to this,
while planning i.e. while
planning any project,
some cost is incurred, some expenditure is incurred,
that expenditure is shown here, similarly
expenditure will be incurred during the construction work too,
whether it is in concrete or not. Be it
in purchasing the locomotive, be it in
installing the power supply, in whatever way it is an
expense, if it is developed, then it becomes an
expense. After that, when we
go into the operation maintenance phase, our revenue starts,
we get something from that project.
Returns start coming and
these returns may or may not increase with time,
but
expenses are also incurred during the operation maintenance phase, we
call it Operation and Maintenance Cost,
keeping this entire picture in mind.
We decide whether this
project is economically logical, whether it
should be done or not, and when we do this
decision making from the economic point of view or
economics point of view,
then the tools and
information we need are included in it.
We will start discussing them today.
We have already said that in this entire
course our
focus will be mainly on the construction phase
but this picture has been put to give you a total picture,
so let us move ahead and
see that the investment or The value of the project
depends on the following. What is the value? What does it
depend on? Analysis of the
quantity and time of cash flow expected from the project,
i.e. the quantity that we have considered that
we will get this much return at this time, this much will be our expenditure,
what is its quantity and that
Analyzing when it will happen on the time axis and
also the uncertainty associated with each part of the cash flow,
it is also certain that we
cannot decide whether we will get this much revenue,
if we talk about the highway project,
how much of it will be
Our revenue there will depend on both the things, whether there is traffic, how much toll there is, whether there is traffic in our bus, there is so
much toll in our bus
that we can decide whether our
toll will be 00 or 50, but there is
very little control over the traffic. Literally, if we are
talking about what will happen after 10 years or 15 years,
then there is an uncertainty in it. Even during the
construction work, there is
an uncertainty while executing various works.
Price of steel, price of cement, salary of labor,
all this is done very carefully. Risks can change and to
keep them in mind is to
keep uncertainty in mind. Risk Management is
a subject
which is studied but we will
not go into risk management in this course for now, we will assume that The value
or
figure that we take is stable and does
not involve uncertainty. Keeping in mind the rising cost of maintenance,
investment options should be
evaluated on the basis of the
entire life cycle cost of the project apart from the initial investment
i.e. simply
saying that It is not about whether it will cost
Rs 4 crore or Rs 50 crore to complete this project,
but we should evaluate it on the basis of what will be the life cycle cost of the project in its entire
life span i.e. in service life
and that is
why you should get that complete estimate. The picture was shown once
when the investor earns more than the investment cost
then value is created
i.e. if we completed a project by investing Rs 100 crore
but its returns
came to the value of Rs 110 crore
then it was a profitable deal, it means
Value is created
by the project and the selection of the project
should be such that the project not only
creates value but it creates more value
than any other project with similar uncertainty.
If we have
different options then Among those options,
we should choose the country in which more value is being created. All these things have become
very important in India in the last 2530 years
because
in all the projects, the
government
is encouraging this thing. That if various
private investors invest in projects,
then
what is the meaning of investing in projects, they will also incur costs in the construction process,
whereas earlier in the big
projects, the
government used to invest the cost, the government used to
invest money and hence there is cost benefit
analysis in it. It was done in another way,
but when an investor invests money in it, it becomes
necessary to keep all these things in mind. Let us
move ahead to the time value
of money, which is the
main topic of our today's lecture. What is the
meaning of focus? The value of money keeps changing with time, that is,
what will be the value of Rs. 00 that we have today, tomorrow?
If we try to understand in simple language,
then when we keep Rs. 00 in the bank and the
bank Whatever interest we give on ₹ 5 at ₹ 7,
then ₹ 00
becomes ₹ 1078, but after one year, is the
value of that ₹ 8 or ₹ 10 more than today's ₹ 1
or not? Its value changes
if we say inflation. Inflation means
its value is decreasing due to
inflation and its quantity is increasing due to interest rate, so keep
these things in mind and take
decisions keeping these things in mind. This
comes in the review of our construction economics,
this is what we will discuss. After all, what
is interest? We can see interest as the amount given to the owner of the money for
not being able to use the money or not to use it.
When the bank says that you keep Rs. 00
with us, we will give you Rs. So, the
interest is earned but
you cannot use the money which is yours in that period,
then it is a kind of compensation,
that is
interest. For any investment, there is present value
and future value. Present value and
future. What
is value? We have seen that when we
make a cash flow diagram or picture on time access,
it is a picture that lasts for many years. There is a
planning phase, a construction
phase, an operation maintenance phase, so
it includes the changes that
occur over time. The change in the value of money
cannot be ignored, it has to be
kept in mind, so to keep this in
mind or
keeping this in mind, if we evaluate the
expenditure here or the income here. If
we want then what we have to do is that
we take this quantity as present, whether it is
here or it is here, whatever
present time we take, we
take the present time here, it is
necessary to know what is its value and this is the
change of value or To find out the change,
we should know the interest rate. What is the
interest rate value? We consider it at 5, we
consider it at 10, whatever but if
we know the interest rate then we can decide
that here which is 00.
What will be its today's value? Now the way I have
made it, so here this A and this B, so A
is ahead in time, suppose we take this time of two years,
then think about whether the
current value of A and B.
I am leaving this question for you, which of these values will be higher, so let
us try to understand this through an example.
A
cash flow diagram is given here, outflow i.e.
expenditure and inflow i.e. revenue. The revenue is
shown. It is shown here that there will be an
expenditure of Rs 10 lakh and this is our expenses on year 1 doti ch
pa 6 sa and this is
our revenue. Now what has to be decided is the
present value or the future value of this investment.
Now decide this. What we have to do is what is the
present value or future value of this investment? Is the
investment to be made logical
if we know that we have to spend Rs 10 lakh,
here we will get 2 lakh,
here we will get 500, here we will get 3 lakh, here we will
get one lakh. We will get Rs. 4 lakhs and this will be our
expense, so should we do this project
or not, so it is necessary that
we either bring all these figures to the point
that what is their present value,
we also have to bring it to the present value only. Let us
look at another example. Suppose there are
two projects A and B. Project A has
higher initial cost and annual maintenance
cost is lower while Project B has
lower initial cost but
higher annual maintenance cost. As an investor
which project should you choose? This is
not only for projects, any
construction
equipment, whether it is a crane or an earth
mover, there is a challenge while purchasing it
that we have two options,
one is a machine, the other is a machine, one is the initial of the machine.
Cost: Initial cost of one is
less, one is more but maintenance cost of both is
different, so how will we model it
and how will we take decisions, then
we will have to convert this type of
text into cash flow diagram.
Project A has to be done in
which the initial cost is high so the
cost is high and the maintenance cost is
low.
In comparison, we can say that the
initial cost of Project B is
less but the maintenance cost is less.
Now to choose one of these two options
it is necessary that we calculate the
present cost or present value present
value of these two options at any point in time
and then take the decision and this In this context, it is
important to consider the time value of money. It
must be kept in mind. Now when it
comes to how interest can be calculated,
unless the interest is known,
we cannot calculate the present
value or future value. If we cannot talk about value
then it is necessary to calculate interest. It is
necessary to understand about it.
We calculate interest on the basis of single payment.
Compound amount factor and
present worth factor are two terminologies.
Based on that we learned in high school. We have
read about compound interest and simple interest, what happens in it is
that if we pay an amount a
simple
interest whose rate is t,
if we keep it for t time
then what will be the simple interest. We
can calculate this, we have been taught this in high school.
In comparison, when it comes to
compound interest, we
calculate that whatever interest will be earned on the same amount at the same
rate in the first year or first time span. That
amount will come and will be added to this amount and then this amount
plus interest will again be interest on it
and when our next interest will come then this
is the matter of compound interest.
To calculate this also we did different types
of exercises in high school.
We will discuss the same things
in a slightly different perspective.
After single payment, comes the issue of
equal payment. It is not necessary that
we are talking about one lump sum payment,
often we discuss about equal payment. It is
based on that
i.e. we may get some revenue continuously and
sometimes we may have some expenditure continuously, so to
understand the model,
this thing has been equalized. It is
not necessary that it should be equal.
Mathematics becomes easy.
This calculation is very easy but it
requires computer or excel sheet. There are
many factors. There are many
tables available from which we
can do these calculations but today we
will try to do these calculations ourselves
so that If you understand what we
want to do and how the factors are
calculated then
in Equal Payments we will talk about these four namely Compound Amount Factor, Present
Worth Factor, Sinking Fund Deposit and
Capital Recovery Factor.
So let us first talk about The
simple thing about Single Payment Compound Amount Factor is that we have one amount at one place in time and
another amount at another place. There is
a time in between which is
given in t years and there is a rate of
interest. There is a relationship among the four parameters,
that relationship itself is being
analyzed. Single Payment
Compound Amount Factor, which is called SPCF,
what is that given
p i and
then we know p, we know a, we
know n, our The principal that we have
taken in the beginning is Aa, which is the rate of
interest that we will take and n is the
measure of our time. If we are talking about n years,
then there
we know that SPC F1 is equal to the power of n. Where the
percentage has been taken,
as an example, if we see how much the deposit amount of Rs
10 lakh will increase in five years at the interest rate of 8%,
then it has been done in our high
school that
we will apply compound interest. And we'll do pi times pi
multiplied by pi to the power a and we'll
see that it becomes 14 69 328 so if we
remove this thing, our factor
comes out to be
1.46
so if we know pi and a then we can
factor this. You can find out F and if you know the factor
then you
know your principal amount, you will have no problem in finding F.
If we turn this thing around and say that
we know F, we want to know
how much P should we keep.
Then what we have to do is
reverse the previous process then it will become N upon 1
ps i to power A. Example of this
if we see that if it is assumed that the
value of a property after 10 years will be Rs 20 lakh
then what is the present value of the property
? Let us assume that the interest rate is Rs 10 per annum,
then if we assume this then its value will be
Rs 7716. If we look at this from the perspective of construction, then if we see that we have to buy a machine here, the cost of which will be Rs 10 lakh. If we assume, then
how much money do we need today which
we can set aside at an interest rate so that
after n years we get that F amount.
We call this as Single Payment Present Worth
Factor. So what is the present value of this amount?
What is the present value of this
Present value of lakh is Rs 7 lakh. Moving
ahead, we talk about equal payment compound
factor. EP CF. What does it
mean that Ai and A means that
if we keep this a continuously every year, then what will
be A and Aa and A. We know. I and A means
rate of interest and number of years so if
we know this thing then we
can calculate EPC F with this formula
if we try to understand it and
say a1 a2 a3 a4 or here A If it is -1 then we
write n-1, then
we pay these installments, then who is contributing how much in this F. The one
who is a1 is contributing
for so much time, the one who
is a2 is contributing for one year less i.e.
A3 is doing it for this much time and for one more year less and
this is the last
installment and this is the last installment, he is
doing it only for one year, so a1,
a2, a3 etc. till A-1.
Looking at the contributions or if we
add up everyone's contributions, then the value that will come will be A. So
this is the value which is a1 a2 a3 a4. If
we keep a rate of interest for n years
then what will be its F. So we can call it Let us
see through an example what will be the value at the end of 10 years for a
simple annuity of Rs. 00 operating on compound interest at the annual compound rate of 8%.
If we use this formula,
then the value we get is
2897 32 We invested. 20000 10
years ₹ lakh and we got 2 lakh
8972 i.e. the value we got
is our interest, here we made equal payment, so the
example we had taken earlier is that
if our construction equipment is worth 20 lakh
and we want to buy it after 10 years.
or want to buy it after 4 years,
then one way is that we can keep this money somewhere in lump sum
and after so many years we will get this money,
another option can be that we will
not be able to keep this much amount here but we can keep a
little amount here. Let's keep it so that
we can buy this equipment after so many years. Let's
move ahead. Equal Payment Sinking Fund
Deposit Factor.
FI&A given here. How much should our A be?
This is a little different from the previous example.
What was the last time?
A given here. Here we have been
given f and we have to find a, so the
example I explained to you is more relevant from this point
that we know f that
we need to buy 20 lakh equipment,
what amount should we calculate for it?
Which amount will have to be removed or
which amount should we put in a sinking fund and
forget about it? Just
like we talk about a coin with children, we keep the
money aside and
do not touch it, then we will put that coin in a sinking fund.
What amount should we put in the form every year so that
after A years we get F, this is our
formula, for that let us see the example of
how much should be invested in the bank every year to make an amount of Rs 20 lakh at the end of 20 years. It
should be assumed that the
rate of compound interest is at 8. In this entire
discussion, you must be seeing that the rate of
interest is that we have to continuously believe that
without the rate of interest,
nothing will happen but this is also certain, is it
uncertainty? We should also keep in mind what the rate of interest
will be at what time
and follow a conservative value.
This is a principle that every
project manager should keep in mind
while making decisions. Keep in mind that we are
on a conservative side. We are moving
on the side of a risk, let's move ahead. The
answer is that if we want 20 lakh rupees
at the end of 20 years, then we will have to
separate 3705 rupees every year and the
factor of yours comes out of this here.
We call the value coming from EP
SADF That is Equal Payment Sinking Fund
Deposit Factor. All these factors are available in the form of a table for
different rates of interest
so we do
not need to do this calculation every time. So
let's move on to the next factor. Let's talk about Equal
Payment Present Worth Factor. Now we are
talking about Present Worth. Till now
we have talked about Future Worth that what is A. Now we
will talk about Present Worth i.e. if we do this for
n consecutive years at different rates of interest. If we
do this then we can use this formula
to find out what is the present value of this investment. For
example, we see that
what is the present value of ₹ Haj Ordinary Annuity invested for a period of 10 years?
Present value means present. So,
what is its value at this time? If we
use this formula, then our
present worth comes out to be
1.3426, so the present value of this entire investment
is 3260. Keep in mind that if we are
investing 00 in 10 years, then our total The
investment is of Rs 2 lakh, but the
present value of this Rs 2 lakh
is only Rs 1,3260. This means that
if we call these values a1, a2, a3 etc.,
then what is their value here? What is the
value of this 00 here? How much is it? If we
calculate the present worth, then we will calculate it by
adding all these values. So let's move ahead and
this last factor is the equal payment capital
recovery factor in which p, a and n are
given and if a is to be calculated, then as I
told you earlier, this is the game. The value
here is of only four quantities
i and the value here. The second thing is that
whether we take this value in perpendicular or we give it to the
distributor, when we
give it to the distributor, then they make equal amounts.
It is not necessary that there should be equal amounts.
If these amounts are unequal then
we can convert all these values into present worth
factor as I told you but for that
you will have to do a little mathematics and
we will give you an exercise in homework
so let's go back. Let
us see an example on equal payment capital recovery factor
i.e. the number of years is n which is
6 years and the rate of interest is 4.
To decide the recovery of Rs 2 lakh i.e.
our p is given. 2 lakhs, to
neutralize it we have to decide the annual installment
i.e. we have to decide A, for this
if we use this formula then
we come to know that 38000 is 50 then
8150 if we pay for 6 years then we get
2 Now you
can see that there is a loan of Rs. lakh, we will
give him Rs. 8150 for 6 years, when our loan will end,
then how much interest component we have given,
you can calculate the interest rate is given.
But
you can find out from here how much is the component of total interest, so we would
like to end today's discussion here
where we have discussed about interest and interest rate,
present worth, future worth and equal
installments.
Further we will discuss about these things.
How do we take financial decisions,
on what criteria do we take them, how do we interpret those criteria, we will
continue the discussion on this in the next lecture. This is a
list of useful published books.
I suggest you to check them out.
Thanks Jai